Old River Crossing - Tunneling Shaft Depressurization Design
Worked with Malcolm Drilling to value engineer an alternative shaft construction method that deviated from the “wet construction” method specified in the contract documents. The 100-ft deep launching shaft penetrated and was underlain by multiple confined aquifers, each with groundwater levels close to the ground surface. Malcolm Drilling’s proposed construction method required depressurization of the underlying confined aquifers to ensure integrity of the base of the shaft during construction. Complex alluvial subsurface conditions along with stringent drawdown and settlement restrictions required development of a three-dimensional groundwater flow model to assess the depressurization effects in the multiple soil units.
Implementation of our depressurization design resulted in groundwater levels and ground settlements within our original estimates which were considerably lower than the design team’s conservative estimates. Malcolm Drilling was allowed to proceed with its construction method, which provided the project owner with an improved final product while significantly reducing Malcolm’s construction costs.
City Creek Center- Dewatering Design
Developed a Groundwater Control Plan and dewatering design for the City Creek Center project which was one of Salt Lake City’s largest construction project in the last 25 years. The project consisted of a mass excavation occupying one city block and extending 70 ft below grade and 25 feet below the local groundwater table. Alternating coarse and fine-grained soils in conjunction with existing building foundations and multiple shoring methods did not allow implementation of traditional deep dewatering wells.
By integrating passive groundwater control effects of the shoring, construction sequencing, and various vacuum wellpoint systems the excavation was successfully dewatered without delaying shoring and excavation production. A deep confined aquifer also required groundwater control measures as certain structural excavations extended into the aquitard. A depressurization system consisting of deep wells was implemented to control uplift pressures on the subgrade completed within the aquitard.
Sound Transit Capitol Hill Station – Dewatering and Depressurization System Design
Designed a Groundwater Control System to depressurize and dewater the subsurface station box during tunneling and station construction phases. The temporary station box served as a portal for launching and receiving tunnel boring machines used to construct side by side running tunnels. Temporary shoring for the station box consisted of soldier pile and lagging installed around the perimeter of the excavation (540 ft long by 100 ft wide). The excavation extended about 85 below grade which exposed a 35 ft confined aquifer with a piezometric head of about 60 ft above the bottom of the excavation. The base of the aquifer coincided with the proposed subgrade therefore requiring depressurization and complete dewatering of the confined aquifer.
A system of deep wells installed around the perimeter of the excavation provided initial depressurization and partial dewatering of the confined aquifer which allowed the excavation to progress to within 20 ft of the proposed subgrade. A vacuum wellpoint system installed through the shoring wall dewatered the remainder of the confined aquifer allowing the excavation to reach final subgrade.
Bravern Construction Dewatering System Design and Monitoring
Worked with the shoring contractor and shoring designer to value-engineer a shoring/dewatering system for a city-block excavation that extended 90 ft below grade. Groundwater levels had to be lowered 30 feet to implement the proposed soil-nail shoring system. Strategic placement of deep dewatering wells working in conjunction with a wellpoint system at the base of the excavation eliminated wells within the interior of the excavation which were originally deemed necessary by the Project Owner’s geotechnical consultant.
Implementation of our depressurization design resulted in groundwater levels and ground settlements within our original estimates which were considerably lower than the design team’s conservative estimates. Malcolm Drilling was allowed to proceed with its construction method, which provided the project owner with an improved final product while significantly reducing Malcolm’s construction costs.
Pontoon Construction Facility
WSDOT and HDR/SR 520, Grays Harbor, WA
Developed and managed multiple hydrogeologic assessments during the site selection process for WSDOT’s Pontoon Construction Facility. Upon selection of the preferred site, performed a comprehensive hydrogeologic evaluation which included a pumping test field program, preliminary dewatering design, and cost estimate for the temporary and permanent dewatering systems. Developed a site-wide three-dimensional finite difference groundwater model for evaluating various groundwater control methods (pumping and cutoff) for temporary and permanent dewatering systems. The preferred site consisted of a 55 acre parcel situated next to Grays Harbor. Subsurface conditions consisted of very soft cohesive soils with interbedded granular soils for the upper 70 feet. The proposed open cut mass excavation would encompass over 10 acres and extend 30 feet below the groundwater table.
North Creek Sewer Replacement Pre-Design – Dewatering Evaluations
Performed dewatering feasibility studies for alternative alignments for 3.1 miles of sewer in Bothell, Washington. Upon selection of the preferred alignment project work involved, development of dewatering requirements and discharge rates for open cut and micro tunnel access shafts, preparation of dewatering/depressurization specifications, and performance of a baseline characterization of residential wells proximate to the alignment. The proposed subgrade was situated just above a thin aquitard that confined a deeper aquifer with groundwater pressures 18 ft above ground surface or 33 ft above proposed subgrade. Analyses included determining most appropriate approach for construction dewatering and depressurization, evaluation of dewatering discharge disposal options and cost estimates. Final design studies included installation of deep confined aquifer observation wells, pumping tests, and estimation of dewatering discharge quantities.
Brightwater Treatment Plant Construction – Groundwater Control Assessment and Oversight
Evaluated the groundwater control requirements to complete mass grading and deep excavations of a new 36 MGD reclaimed wastewater treatment plant situated on a 43 acre site. Designed dewatering and depressurization systems for the mass and structural excavations which were incorporated into a prescriptive dewatering specification. Dewatering/ depressurization systems included deep pumped wells, vacuum wellpoint systems, and eductor/ejector wells.
Headworks and Secondary Activated Sludge Facility – Third Party Construction Dewatering Evaluation
Evaluated Contractor’s designed dewatering system as well as the Contractor’s proposed supplemental systems for a 300-ft by 900-ft, 33-ft deep excavation that could not be dewatered. The evaluation identified that the initial system did not account for the limited aquifer thickness below the excavation and the Contractor’s proposed approaches would also prove ineffective. Additionally the evaluation identified excessive confined groundwater pressure from deeper aquifers that were likely contributing recharge to the excavation and would have destabilized the subgrade once exposed.
OCSD P2-90 Clarifiers and Trickling Filters – Dewatering Evaluation
Evaluated District’s consulting engineer’s geotechnical and hydrogeologic reports to assess most appropriate approach for dewatering approximately 400-ft by 200-ft excavation adjacent to the Santa Ana River. Provided report outlining anticipated dewatering issues and prepared comprehensive set of technical specifications for a contractor designed dewatering system. Completed assessment and specifications within a four-week turn around to allow insert into addendum for project already advertised for bidding.